K.4 Project/mission closure
1) Clean EQ :
- Transfer all EQs to another location (ask MEMO team for international transfer)
- Put in OUT quickly or transfer Generator and vehicle to stop the need to record the fuel consumption
- Check if there isn’t EQ under SAV in the project : if yes, transfer under another project (for the mission : inform MSF logistics you aren't waiting to send back the EQ en SAV)
2) Clean Additional EQ:
- Transfer all additional equipment under the new location or put them in OUT (ask MEMO team for international transfer)
3) Clean Maintenance and WO:
- Cancel all WO under a user of the project
- In external maintenance : control if there isn’t pending contract with EQ
- Change the person in charge of all maintenance plan (not user from the project which is closing) > use the report “verification of maintenance plan”. (for the mission : change all preventive maintenance "inactivate")
4) Clean Staff and companies:
- Staff : deactivate all staff of the project (ask MEMO team)
- Company : deactivate all companies we worked with (check end of contract)
5) Delete others elements:
- Request for delete the location in MEMO (MEMO will transfer OUT EQ in the root of the mission before)
- Request for delete MEMO user in MEMO
6) Do an inventory to the others projects