F.1.2 Re-schedule a group of maintenance plan
Situation 1 : According to the planning of schedule between 2 dates : You are going holiday or for a training… and you don’t want to have WOs created during this period : you need to change the schedule of all maintenance plans during this period
Situation 2 : According to the location : all biomed EQ in the OT need to be re-scheduled to another week
Situation 1 : between 2 days
- Go to the application ALL FAMILIES SCHEDULE in MAINTENANCE module
- With Criteria Filter : select the next launch date after the beginning of your planned absence, and the date that you will come back, then select status “actif” + search
- Open the 1st maintenance plan of the list
- Change the date of the next maintenance and save it
- Click on the arrow
to move to the next maintenance plan.
- Repeat steps 4 and 5 until the end.
Situation 2 : by location
- Go to All families schedule in Maintenance module
- Filter by the location you are concerned with
- Open the 1st maintenance plan
- Change the date of the next maintenance (and copy it)
- Click on the arrow
to move to the next maintenance plan
- Paste the date of the previous maintenance plan
- Repeat steps 5 and 6 until the end