Situation 1 :  According to the planning of schedule between 2 dates : You are going holiday or for a training… and you don’t want to have WOs created during this period : you need to change the schedule of all maintenance plans during this period

Situation 2 : According to the location : all biomed EQ in the OT need to be re-scheduled to another week 



Situation 1 : between 2 days


  • Go to the application ALL FAMILIES SCHEDULE in MAINTENANCE module 
  • With Criteria Filter : select the next launch date after the beginning of your planned absence, and the date that you will come back, then select status “actif” + search



  • Open the 1st maintenance plan of the list
  • Change the date of the next maintenance and save it
  • Click on the arrow to move to the next maintenance plan. 
  • Repeat steps 4 and 5  until the end. 



Situation 2 : by location


  • Go to All families schedule in Maintenance module 
  • Filter by the location you are concerned with
  • Open the 1st maintenance plan 
  • Change the date of the next maintenance (and copy it) 
  • Click on the arrow to move to the next maintenance plan
  • Paste the date of the previous maintenance plan
  • Repeat steps 5 and 6 until the end